How to Prepare a Construction Bid Summary and Formal Quotation

A step-by-step guide to assembling a complete construction bid — from direct costs through subcontractors, overhead, contingency, profit, VAT, and a client-ready PDF quotation.

A construction bid summary is the final document that consolidates all project costs into a single total that a contractor submits to a client or project owner. It is the culmination of the estimating process — and the document that wins or loses the project.

Components of a Complete Bid

A well-structured construction bid contains the following cost components, assembled in order:

  1. Direct Material Costs — from the BOQ (Bill of Quantities)
  2. Direct Labor Costs — typically 15–30% of material cost depending on trade
  3. Subcontractor Costs — for specialist trades (Electrical, Plumbing, HVAC, Fire Protection, Elevator)
  4. Site Overhead — supervision, temporary facilities, utilities, safety, permits
  5. Contingency — typically 3–5% of the subtotal for unforeseen items
  6. Profit Markup — contractor's margin, typically 8–15% depending on project risk
  7. VAT — 12% in the Philippines (on the sum of all above)
Total Bid = (Direct Costs + Subcontractors + Overhead + Contingency) × (1 + Profit %) × (1 + VAT %)

Direct Material and Labor Costs

Pull these from your discipline BOQs (Electrical, Plumbing, Structural, etc.). Each calculator output gives you a material subtotal. Labor is typically applied as a percentage of materials or from a labor rate schedule.

  • Electrical: 20–35%
  • Plumbing: 25–40%
  • Structural concrete: 30–50% (includes formwork erection)
  • Painting: 40–60% (labor-intensive)

Subcontractor Management

  • Scope inclusion (what's in and out of their price)
  • Material specification compliance
  • Warranty terms and support

Select the winning bid per trade and include it in the bid summary. Common trades to subcontract: Electrical, Plumbing, HVAC, Fire Protection (FDAS), Elevator/Escalator.

Site Overhead

  • Site management salaries and allowances
  • Temporary facilities (site office, storage, sanitation)
  • Temporary power and water supply
  • Safety equipment and signage
  • Construction equipment rental
  • Building permits and licenses
  • Insurance (CARI, Workers' Compensation)

Site overhead typically adds 8–15% to direct costs for medium-scale projects.

Contingency

  • 3% for well-defined projects with detailed drawings
  • 5% for projects with incomplete design or known ground risks
  • Up to 10% for design-build or fast-track projects

Profit Markup

  • 8–10% for competitive public bids
  • 12–15% for private clients and negotiated contracts
  • 15–20% for specialty or high-risk projects

Formal Quotation Format

  • Company letterhead with license numbers (PRC, PCAB)
  • Project description and scope summary
  • Validity period (typically 30–60 days)
  • Cost breakdown table
  • Payment terms
  • Client signature block for approval

Using EngEst Pro

EngEst Pro's Bid Summary module assembles all of this automatically. Link your project's BOQ, subcontractor bids, and site overhead — set your contingency and profit percentages — and export a formal PDF quotation with your company letterhead, complete cost breakdown, and a client signature block, ready for client submission.

Try it in EngEst Pro — free

EngEst Pro automates everything described in this guide. Create a free account — 5 projects/month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account →← More Guides

Related Guides

⚡
How to Calculate Electrical Load for a Residential Building
Electrical · 8 min read
→
📋
Understanding Bill of Quantities (BOQ) in Construction
Estimating · 6 min read
→
☀️
Solar PV System Sizing: From Load Analysis to Panel Count
Solar · 10 min read
→