A construction bid summary is the final document that consolidates all project costs into a single total that a contractor submits to a client or project owner. It is the culmination of the estimating process — and the document that wins or loses the project.
Components of a Complete Bid
A well-structured construction bid contains the following cost components, assembled in order:
- Direct Material Costs — from the BOQ (Bill of Quantities)
- Direct Labor Costs — typically 15–30% of material cost depending on trade
- Subcontractor Costs — for specialist trades (Electrical, Plumbing, HVAC, Fire Protection, Elevator)
- Site Overhead — supervision, temporary facilities, utilities, safety, permits
- Contingency — typically 3–5% of the subtotal for unforeseen items
- Profit Markup — contractor's margin, typically 8–15% depending on project risk
- VAT — 12% in the Philippines (on the sum of all above)
Total Bid = (Direct Costs + Subcontractors + Overhead + Contingency) × (1 + Profit %) × (1 + VAT %)
Direct Material and Labor Costs
Pull these from your discipline BOQs (Electrical, Plumbing, Structural, etc.). Each calculator output gives you a material subtotal. Labor is typically applied as a percentage of materials or from a labor rate schedule.
- Electrical: 20–35%
- Plumbing: 25–40%
- Structural concrete: 30–50% (includes formwork erection)
- Painting: 40–60% (labor-intensive)
Subcontractor Management
- Scope inclusion (what's in and out of their price)
- Material specification compliance
- Warranty terms and support
Select the winning bid per trade and include it in the bid summary. Common trades to subcontract: Electrical, Plumbing, HVAC, Fire Protection (FDAS), Elevator/Escalator.
Site Overhead
- Site management salaries and allowances
- Temporary facilities (site office, storage, sanitation)
- Temporary power and water supply
- Safety equipment and signage
- Construction equipment rental
- Building permits and licenses
- Insurance (CARI, Workers' Compensation)
Site overhead typically adds 8–15% to direct costs for medium-scale projects.
Contingency
- 3% for well-defined projects with detailed drawings
- 5% for projects with incomplete design or known ground risks
- Up to 10% for design-build or fast-track projects
Profit Markup
- 8–10% for competitive public bids
- 12–15% for private clients and negotiated contracts
- 15–20% for specialty or high-risk projects
Formal Quotation Format
- Company letterhead with license numbers (PRC, PCAB)
- Project description and scope summary
- Validity period (typically 30–60 days)
- Cost breakdown table
- Payment terms
- Client signature block for approval
Using EngEst Pro
EngEst Pro's Bid Summary module assembles all of this automatically. Link your project's BOQ, subcontractor bids, and site overhead — set your contingency and profit percentages — and export a formal PDF quotation with your company letterhead, complete cost breakdown, and a client signature block, ready for client submission.