โšก Electrical ยท 8 min read

How to Calculate Electrical Load for a Residential Building

A step-by-step guide to computing connected load, demand load, cable sizing, and panel schedule for a residential construction project.

Electrical load calculation is the starting point for any residential wiring design. Before you can size cables, select circuit breakers, or specify a distribution panel, you need to know how much power your building will consume under normal operating conditions.

Step 1: List All Electrical Loads

  • Room name and circuit description
  • Load type (lighting, outlet, aircon, appliance)
  • Quantity of units
  • Watts per unit (from manufacturer nameplate or ASHRAE/NEC tables)

Step 2: Compute Connected Load

Connected Load (CL) is the sum of all loads running simultaneously at full rated power. For each circuit:

CL = Quantity ร— Watts per Unit

Sum all circuits to get the total connected load in watts (W) or kilowatts (kW).

Step 3: Apply Demand Factors

  • General lighting: 100% for first 3kVA, 35% for remainder
  • Receptacles: 100% first 10kVA, 50% remainder
  • Air conditioning: 100% (apply to the largest unit only if multiple)
  • Fixed appliances: 75% if 4 or more
Demand Load = Connected Load ร— Demand Factor

Step 4: Calculate Running Current

Convert demand load to amperes for cable sizing:

I = P / (V ร— PF ร— โˆš3) [for 3-phase] > I = P / (V ร— PF) [for single-phase]
  • P = demand load in watts
  • V = voltage (230V for single-phase, 400V for 3-phase line-to-line in the Philippines)
  • PF = power factor (typically 0.85โ€“0.90)

Step 5: Select Cable Size

With the running current computed, select THHN copper conductor size from PEC Table 3.10.1, choosing the next size up from your computed current. Apply correction factors for ambient temperature and conduit fill if applicable.

Step 6: Verify Voltage Drop

PEC limits voltage drop to 3% for branch circuits and 5% cumulative. Use the formula:

VD% = (2 ร— L ร— I ร— R) / V ร— 100 [single-phase]

Where L = one-way cable length (meters), R = resistance per meter of selected cable (ฮฉ/m).

If voltage drop exceeds the limit, upsize the cable.

Step 7: Size the Panel and Transformer

The main distribution panel (MDP) rating must exceed the total demand load by at least 25% for future expansion. For a transformer:

kVA Rating = Total Demand Load (kW) / PF

Select the next standard transformer size above your calculated kVA.

Using EngEst Pro: EngEst Pro automates every step above โ€” enter your circuit schedule, set the demand factors, and the platform computes connected load, demand load, cable sizes, panel schedule, transformer kVA, and generator sizing, then exports a complete electrical BOM in your local currency.

Try it in EngEst Pro โ€” free

EngEst Pro automates everything described in this guide. Create a free account โ€” 5 projects/month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’โ† More Guides

Related Guides

๐Ÿ“‹
Understanding Bill of Quantities (BOQ) in Construction
Estimating ยท 6 min read
โ†’
โ˜€๏ธ
Solar PV System Sizing: From Load Analysis to Panel Count
Solar ยท 10 min read
โ†’
๐Ÿšฟ
Plumbing Pipe Sizing Using Hunter's Method
Plumbing ยท 7 min read
โ†’