Electrical load calculation is the starting point for any residential wiring design. Before you can size cables, select circuit breakers, or specify a distribution panel, you need to know how much power your building will consume under normal operating conditions.
Step 1: List All Electrical Loads
- Room name and circuit description
- Load type (lighting, outlet, aircon, appliance)
- Quantity of units
- Watts per unit (from manufacturer nameplate or ASHRAE/NEC tables)
Step 2: Compute Connected Load
Connected Load (CL) is the sum of all loads running simultaneously at full rated power. For each circuit:
CL = Quantity ร Watts per Unit
Sum all circuits to get the total connected load in watts (W) or kilowatts (kW).
Step 3: Apply Demand Factors
- General lighting: 100% for first 3kVA, 35% for remainder
- Receptacles: 100% first 10kVA, 50% remainder
- Air conditioning: 100% (apply to the largest unit only if multiple)
- Fixed appliances: 75% if 4 or more
Demand Load = Connected Load ร Demand Factor
Step 4: Calculate Running Current
Convert demand load to amperes for cable sizing:
I = P / (V ร PF ร โ3) [for 3-phase] > I = P / (V ร PF) [for single-phase]
- P = demand load in watts
- V = voltage (230V for single-phase, 400V for 3-phase line-to-line in the Philippines)
- PF = power factor (typically 0.85โ0.90)
Step 5: Select Cable Size
With the running current computed, select THHN copper conductor size from PEC Table 3.10.1, choosing the next size up from your computed current. Apply correction factors for ambient temperature and conduit fill if applicable.
Step 6: Verify Voltage Drop
PEC limits voltage drop to 3% for branch circuits and 5% cumulative. Use the formula:
VD% = (2 ร L ร I ร R) / V ร 100 [single-phase]
Where L = one-way cable length (meters), R = resistance per meter of selected cable (ฮฉ/m).
If voltage drop exceeds the limit, upsize the cable.
Step 7: Size the Panel and Transformer
The main distribution panel (MDP) rating must exceed the total demand load by at least 25% for future expansion. For a transformer:
kVA Rating = Total Demand Load (kW) / PF
Select the next standard transformer size above your calculated kVA.