Estimate Classes — Conceptual, Preliminary, and Definitive

An estimate’s accuracy is bounded by the design behind it. Knowing which class you are producing keeps expectations — and contingencies — honest.

The classes

ClassDesign maturityMethodAccuracy
5 — Order of magnitude0–2%Cost/m², capacity factors, analogy−30% to +50%
4 — Conceptual1–15%Elemental cost per functional unit−20% to +30%
3 — Preliminary / budget10–40%Elemental + major measured items−15% to +20%
2 — Detailed / control30–75%Semi-detailed BOQ, priced−10% to +15%
1 — Definitive / bid65–100%Full BOQ from drawings and specs−5% to +10%
Advertisement

Matching contingency to class

Contingency covers the known unknowns for that maturity — not scope changes, and not a hidden profit buffer.

Using the right one

A feasibility study needs a Class 4, fast and cheap. A tender needs a Class 1, slow and rigorous. Presenting a Class 4 number with Class 1 confidence is how projects get approved on a budget they cannot be built for.

📋 Using EngEst Pro

EngEst Pro supports the full range — the Conceptual Estimate for early Class 4/5 budgeting by building type and area, and the Cost Estimator for a full Class 1 BOQ from measured quantities.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account — 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account → Run your first estimate in under 10 minutes.