Every line in a BOQ has a rate. Building that rate from its parts โ€” rather than pulling it from a price book โ€” is what lets you defend and adjust it.

The structure

Unit rate = (Material + Labour + Plant + Subcontract) × (1 + overhead%) × (1 + profit%)

Build the direct cost per unit first, then apply mark-ups.

Advertisement

Material

Material/unit = (quantity per unit × (1 + waste%) × supplier price) + delivery + unloading + storage loss

Example โ€” 1 m³ of 1:2:4 concrete: 7.3 bags cement + 0.44 m³ sand + 0.88 m³ gravel + water + admixture, each at current price, plus 4% waste.

Labour

Labour/unit = crew hours per unit × all-in hourly rate

Plant and equipment

Owned or hired plant, per unit of output: (hourly plant cost + operator + fuel) / output rate. Include mixers, vibrators, pumps, hoists, compaction plant โ€” whatever the activity needs.

Overhead and profit

Worked skeleton

Concrete in slab, per m³:
Material 4,300 + Labour 900 + Plant 350 = 5,550 direct
× 1.10 overhead = 6,105 × 1.12 profit = 6,838 / m³
๐Ÿ“‹ Using EngEst Pro

EngEst Pro builds unit rates from material, labour, and plant components with your local prices and output rates, then applies overhead and profit โ€” every BOQ line shows the build-up, not just the final number.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.