Preliminaries and General Requirements in a BOQ

Preliminaries are where thin bids get thinner and where realistic bids protect themselves. They deserve a proper build-up, not a percentage.

What’s in it

GroupExamples
Management & staffProject manager, engineers, foremen, safety officer, QS, admin
Temporary facilitiesSite office, stores, mess, toilets, fencing, signage, hoarding
Temporary servicesPower, water, telecoms, drainage, lighting
Common plantTower/mobile crane, hoist, pumps, generators, small tools pool
Access & enablingScaffolding (if not in trades), site roads, laydown
Safety & environmentPPE, barriers, dust/noise control, spill kits, first aid
CompliancePermits, testing, surveys, as-built documentation, handover
CommercialInsurances (CAR, third-party), performance bond, retention bond
Advertisement

Time-related vs fixed

Splitting them this way makes extension-of-time claims and value-engineering assessments straightforward.

Pricing method

Preliminaries = Σ(time-related rate × duration) + Σ(fixed lump sums)

Cross-check the total against 8โ€“15% of the works value โ€” outside that band, something is missing or double-counted.

๐Ÿ“‹ Using EngEst Pro

EngEst Pro’s Site Overhead tracker itemises preliminaries โ€” supervision, temporary facilities, utilities, safety, equipment, permits, insurance โ€” as time-related and fixed costs that roll into the Bid Summary.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.