๐Ÿ“‹ Estimating / BOQ ยท 6 min read

Structuring a BOQ by Trade Section

A BOQ’s structure is a shared language. When every bidder prices the same sections in the same order, comparison is fast and disputes are fewer.

Standard section order

  1. Preliminaries / general requirements โ€” site setup, management, temporary works, insurances
  2. Demolition & site clearance
  3. Earthworks
  4. Substructure โ€” foundations, ground slab, basement
  5. Superstructure โ€” frame, upper floors, roof, stairs
  6. External envelope โ€” walls, windows, doors, cladding, waterproofing
  7. Internal finishes โ€” partitions, plaster, floor/wall/ceiling finishes, painting
  8. Fittings & fixtures / joinery
  9. Services โ€” plumbing/sanitary, electrical, mechanical/HVAC, fire protection, lifts
  10. External works โ€” pavements, drainage, landscaping, boundary
Advertisement

Preliminaries vs measured work

Preliminaries are project-wide costs not attributable to one item โ€” site office, cranes, scaffolding, supervision, security, testing. Keep them out of the unit rates so the measured rates stay comparable and re-usable.

Provisional sums and PC items

Numbering

Number sections and items hierarchically (e.g. 5.2.3). Keep the item reference stable through addenda so “item 5.2.3” means the same thing in every bidder’s return and in the contract.

๐Ÿ“‹ Using EngEst Pro

EngEst Pro organises the Cost Estimator BOQ by category and work section, keeps preliminaries and site overhead separate from measured rates, and supports provisional sums so the bill compares cleanly across bidders.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.