Estimating Retaining Wall Concrete, Rebar, and Backfill

A cantilever retaining wall is a repeating cross-section. Estimate one metre of wall completely, then multiply along the length with adjustments for height changes.

Concrete per metre of wall

Stem = average stem thickness × stem height
Base = base thickness × base width (heel + toe + stem)
Key (if any) = key depth × key width
Total m³/m = stem + base + key

Stems often taper โ€” use the average thickness. Break the wall into height bands and estimate each band’s cross-section.

Advertisement

Reinforcement

Convert to kg/m of wall by bar diameter, then multiply by length and add splice and wastage allowances.

Formwork

Stem: both faces × height. Base: edge forms only if cast in open excavation. Key: two faces × depth.

Backfill and drainage

ItemBasis
Granular backfill behind stemwedge area behind wall × length
Subsoil drain (perforated pipe + gravel)per metre along the heel
Weep holes1 per 1.5โ€“3 m of wall
Geotextile filter / drainage compositeback-of-wall area
Excavation & disposalto founding level + working space, minus backfill
๐Ÿšง Using EngEst Pro

EngEst Pro’s Structural and Civil calculators handle the retaining wall together โ€” stem and base concrete, two-face rebar, formwork, granular backfill, subsoil drainage, and excavation โ€” as one BOQ section priced per metre of wall.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.