Trench Excavation, Bedding, and Backfill Takeoff by Pipe Size

Trenching is a per-metre calculation once you fix the trench cross-section for each pipe size and depth band.

Trench cross-section

Trench width W = pipe OD + 2 × working clearance (150โ€“300 mm each side)
Trench depth D = cover + pipe OD + bedding thickness

Minimum cover is typically 600 mm under landscape, 900 mmโ€“1.2 m under roads. Add side slope or shoring below the safe vertical depth (~1.2 m in most soils).

Advertisement

Volumes per metre of trench

ItemPer metre
ExcavationW × D (+ slope wedge if battered)
BeddingW × bedding thickness (100โ€“150 mm)
Pipe surroundW × (OD + 150 mm) − pipe cross-section
Selected backfillW × (300 mm above pipe)
Common backfillexcavation − (bedding + surround + selected + pipe)

Spoil balance

Surplus spoil (loose) = [excavation − total backfill (bank equiv.)] × (1 + swell%)

Granular bedding and surround are usually imported, which displaces an equal bank volume of site spoil to disposal.

Extras that belong in the BOQ

๐Ÿšง Using EngEst Pro

EngEst Pro’s Civil Calculator takes off trench works by pipe size and depth โ€” excavation, bedding, surround, backfill, compaction, and surplus spoil โ€” and links reinstatement quantities back into the BOQ.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.