Site Clearing, Grubbing, and Topsoil Stripping Quantities
Site clearing is the first BOQ section and the easiest to under-price. It is more than mowing โ it includes roots, stumps, buried debris, and handling a valuable topsoil layer.
Clearing and grubbing
- Clearing โ remove surface vegetation, brush, and small growth. Measured by area (hectares or m²) of the disturbance footprint plus a working margin.
- Grubbing โ remove roots, stumps, and buried organic matter to a specified depth (typ. 300โ450 mm). Also by area.
Trees
Larger trees are enumerated, usually banded by trunk girth or diameter (e.g. 150โ300 mm, 300โ600 mm, >600 mm), each band with its own rate for felling, stump removal, and disposal. Note any protected trees to be retained and fenced.
Topsoil stripping
- Strip only where earthworks or construction will disturb the ground.
- Stockpile separately, max ~2 m high, away from traffic and drainage, seeded if stored long term.
- Re-spread over landscaped areas at the end โ this is a credit against importing garden soil, and a re-handling cost.
Disposal
Vegetation and grubbed material: chip and reuse as mulch, or haul to a licensed facility. Buried rubble and contaminated material found during grubbing is a provisional item โ flag it rather than absorbing the risk.
EngEst Pro’s Civil Calculator takes off clearing and grubbing by area, topsoil by area and depth, and tracks the stripped topsoil as a stockpile that offsets landscaping import later in the BOQ.
Put this on autopilot with EngEst Pro
Create a free EngEst Pro account โ 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.
Create Free Account โ Run your first estimate in under 10 minutes.