Aggregate course estimating is one conversion done carefully: the drawing gives compacted thickness, the supplier delivers loose material by weight or truckload.

Start from compacted volume

Vcompacted = area × compacted thickness

Take area from the layer width in the typical section (base is narrower than sub-base), and thickness from the pavement design (commonly 150โ€“300 mm per layer, placed in ~150 mm lifts).

Advertisement

Convert to delivered quantity

Vloose = Vcompacted × bulking factor (1.10โ€“1.25)
Tonnes = Vcompacted × in-place dry density (2.0โ€“2.3 t/m³ for crushed aggregate base)

Buy by the tonne where the supplier weighs; by loose m³ or truckload where they do not. Confirm which basis the unit rate is on.

Gradation and standards

Specify the class (e.g. DPWH Item 200 aggregate sub-base course, Item 201 aggregate base course, or the local equivalent) so bidders price the correct crushing and gradation. Sub-base tolerates a wider gradation and more fines; base course is a tighter, stronger crushed product and costs more per tonne.

Wastage

Placement check

Note the number of lifts (compacted thickness / max lift) โ€” it affects the compaction plant hours and the number of density tests, both of which are separate BOQ or preliminaries items.

๐Ÿšง Using EngEst Pro

EngEst Pro’s Civil Calculator converts compacted design volume to loose and to tonnes with your bulking factor and material density, so the aggregate line items match how your supplier quotes.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.