Swell and Shrinkage Factors โ€” Bank, Loose, and Compacted Soil

Soil changes volume when you dig it and again when you compact it. Estimating earthworks means always knowing which state your number is in.

The three states

Advertisement

Conversions

LCM = BCM × (1 + swell%)
CCM = BCM × (1 − shrinkage%)
Load factor = 1 / (1 + swell%)  (multiply LCM by this to get BCM)

Typical values

MaterialSwellShrinkage
Sand / gravel10โ€“15%3โ€“7%
Common earth / loam20โ€“30%8โ€“12%
Stiff clay30โ€“40%12โ€“18%
Blasted rock50โ€“60%−10 to 0% (bulks permanently)

Where each state is used

QuantityState
Excavation paymentBank (BCM)
Haul / truck countsLoose (LCM)
Fill / import requiredCompacted (CCM)
Spoil disposal volumeLoose (LCM)

Cut-fill balance

Import required (BCM) = Fill needed (CCM) / (1 − shrinkage%) − usable cut (BCM)

If the result is negative, you have surplus to dispose of โ€” convert to loose for haulage.

๐Ÿšง Using EngEst Pro

EngEst Pro’s Civil Calculator applies swell and shrinkage factors per soil type automatically, so the earthworks BOQ shows excavation in bank volume, haulage in loose volume, and fill in compacted volume โ€” no manual conversion.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.