๐ง Civil ยท 6 min read
Swell and Shrinkage Factors โ Bank, Loose, and Compacted Soil
Soil changes volume when you dig it and again when you compact it. Estimating earthworks means always knowing which state your number is in.
The three states
- Bank (BCM) โ in place, undisturbed. What the survey measures.
- Loose (LCM) โ excavated, in a truck or stockpile. Larger than bank (it has bulked).
- Compacted (CCM) โ placed and compacted as fill. Smaller than bank.
Advertisement
Conversions
LCM = BCM × (1 + swell%)
CCM = BCM × (1 − shrinkage%)
Load factor = 1 / (1 + swell%) (multiply LCM by this to get BCM)
CCM = BCM × (1 − shrinkage%)
Load factor = 1 / (1 + swell%) (multiply LCM by this to get BCM)
Typical values
| Material | Swell | Shrinkage |
|---|---|---|
| Sand / gravel | 10โ15% | 3โ7% |
| Common earth / loam | 20โ30% | 8โ12% |
| Stiff clay | 30โ40% | 12โ18% |
| Blasted rock | 50โ60% | −10 to 0% (bulks permanently) |
Where each state is used
| Quantity | State |
|---|---|
| Excavation payment | Bank (BCM) |
| Haul / truck counts | Loose (LCM) |
| Fill / import required | Compacted (CCM) |
| Spoil disposal volume | Loose (LCM) |
Cut-fill balance
Import required (BCM) = Fill needed (CCM) / (1 − shrinkage%) − usable cut (BCM)
If the result is negative, you have surplus to dispose of โ convert to loose for haulage.
๐ง Using EngEst Pro
EngEst Pro’s Civil Calculator applies swell and shrinkage factors per soil type automatically, so the earthworks BOQ shows excavation in bank volume, haulage in loose volume, and fill in compacted volume โ no manual conversion.
Put this on autopilot with EngEst Pro
Create a free EngEst Pro account โ 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.
Create Free Account โ Run your first estimate in under 10 minutes.