Rebar is bought by weight but detailed by length and shape. The bar bending schedule bridges the two โ and it is where most steel is over- or under-ordered.
Unit weight by diameter
| Bar (mm) | kg/m |
|---|---|
| 10 | 0.617 |
| 12 | 0.888 |
| 16 | 1.578 |
| 20 | 2.466 |
| 25 | 3.854 |
Cutting length
- Standard hook (90° or 135°): add 9dโ12d per hook.
- Lap splice: add 40d (tension) or 50d in critical zones; count one lap per 12 m bar length for long runs.
- Bend deduction: subtract ~2d per 90° bend, ~3d per 135°, ~0.5d per 45° (the neutral axis shortens on a bend).
Stirrups and ties
One stirrup length = 2(a + b) − bend deductions + 2 hooks (10d each)
where a and b are the tie dimensions to the centre of the outer bars.
Worked slab strip
4.0 m clear span slab, 12 mm main bars at 150 mm c/c, 20 mm cover, standard hooks both ends:
Cutting length = 4000 − 40 + 2(9 × 12) = 4176 mm
Weight = 21 × 4.176 × 0.888 = 77.9 kg (one direction)
Add distribution steel the other way, then 3โ5% wastage and offcuts, and convert to commercial 12 m lengths for ordering.
EngEst Pro’s Structural Calculator builds the bar schedule from element dimensions โ it computes cutting lengths with hooks and laps, stirrup counts, converts to weight by diameter, and outputs RSB quantities per bar size in the BOM.
Put this on autopilot with EngEst Pro
Create a free EngEst Pro account โ 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.
Create Free Account โ Run your first estimate in under 10 minutes.