Formwork is priced by the square metre of contact surface. Each structural element has its own counting convention โ€” get those and the takeoff is quick.

Contact area rules by element

ElementFormwork area
Suspended slabsoffit area (L × W); add edge form = perimeter × thickness
Beam2 × side depth + bottom width, × length (3 faces; deduct slab thickness from sides)
Columnperimeter × height
Wall2 × face area (both sides)
Footing (in open cut)perimeter × depth; nil if cast against earth
Advertisement

From area to materials

Reuse and wastage

State the assumed number of uses in the BOQ โ€” it changes the plywood quantity by 3โ€“5×. Add 10% wastage for cutting around penetrations and damaged panels.

Stripping time affects the estimate

Sides can strip in 1โ€“2 days; slab soffits and beam bottoms need 7โ€“14 days (or reshoring). Longer stripping times mean more sets of formwork on site at once โ€” a hire-cost and quantity driver.

๐Ÿ—๏ธ Using EngEst Pro

EngEst Pro computes formwork contact area per element as you enter slab, beam, and column dimensions, applies your reuse factor, and lists phenolic board, coco lumber, and props in the structural BOM.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.