Cement, Sand, and Gravel Quantities per Cubic Meter of Concrete

This is the single most-used concrete estimating calculation. It rests on one idea: dry loose materials occupy about 1.5 times the volume of the finished concrete.

The dry-volume factor

When water is added, cement paste fills the voids between aggregate and the mix consolidates. To get 1 m³ of compacted concrete you must batch about 1.54 m³ of dry loose materials (1.52โ€“1.57 depending on grading).

Advertisement

Split by the ratio

Sum of ratio parts = C + S + G
Cement volume = 1.54 × C / (C+S+G)
Cement bags = cement volume / 0.0347  (one 40 kg bag ≈ 0.0347 m³)
Sand = 1.54 × S / (C+S+G)  |  Gravel = 1.54 × G / (C+S+G)

Ready reference (per m³, before wastage)

MixCement (40 kg bags)Sand (m³)Gravel (m³)
1:3:64.50.470.94
1:2:46.30.440.88
1:1.5:38.00.420.84
1:1:211.50.400.80

Add wastage and round to delivery units

๐Ÿ—๏ธ Using EngEst Pro

EngEst Pro applies the 1.54 factor and your mix ratio to every concrete volume you enter, adds wastage, and outputs Portland cement bags, sand, and gravel as priced BOM lines in your local currency.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.