A quotation that gets the price right but the payment terms wrong can still sink a contractor. The terms are part of the offer.

Mobilisation / advance payment

Advertisement

Retention

ParameterTypical
Percentage withheld10% of each certified amount
Capoften 5% of the contract sum
First release50% at practical completion / handover
Final releasebalance after the defects liability period (6โ€“12 months)
Substitutionretention bond in lieu of cash withholding

Billing and payment cycle

Claim submitted → certified within X days → paid within Y days

Common terms: monthly claims, certification within 7โ€“14 days, payment within 30 days of certification. Every day added to this cycle is working capital the contractor must fund.

State it in the quotation

๐Ÿ“‘ Using EngEst Pro

EngEst Pro’s Bid Summary and formal quotation PDF include a payment-terms and validity section, and the Progress Billing tracker applies advance recoupment and retention to every claim automatically.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.