Comparing Subcontractor Bids โ€” Scope, Spec, and Exclusions

Subcontractor bids for the “same” package routinely differ by 20โ€“40% โ€” mostly because they are not actually bidding the same thing.

Build a comparison sheet

One row per work element, one column per bidder. Enter each bidder’s price against each element. Blanks are the story โ€” a missing line usually means an exclusion.

Advertisement

Normalise to a common basis

Read the qualifications

“Excludes rock excavation”, “based on continuous access”, “price firm for 30 days”, “excludes testing and commissioning” โ€” each is a risk transferred back to you. List every qualification and price or reject it.

Beyond price

FactorWhy it matters
Capacity / current workloadCan they resource your programme?
Track record on similar workReduces performance risk
Financial standingGuards against mid-contract failure
Programme fitA cheap bid that starts 8 weeks late costs more

Select and record

Choose the lowest normalised compliant bid. Record the comparison and the reasons โ€” it is the audit trail if the award is questioned, and it feeds the bid summary.

๐Ÿ“‘ Using EngEst Pro

EngEst Pro’s Subcontractors module logs multiple bids per trade, lets you record scope and exclusions, mark the winning bid, and rolls the selected subcontractor totals into the Bid Summary automatically.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.