Progress Billing and the Schedule of Values

Progress billing converts physical progress into money owed. The schedule of values is the instrument that makes each claim objective.

The schedule of values (SOV)

Divide the contract sum into line items that map to identifiable work โ€” by trade, by element, or by area. Each line carries a value; the values sum to the contract sum. Front-loading (inflating early items) is a common dispute โ€” keep the SOV proportional to real cost.

Advertisement

Each billing period

Earned this period (per line) = line value × (% complete now − % complete previously)
Total earned to date = Σ (line value × % complete now)

The payment application

LineAmount
Total earned to dateA
Materials on site (if allowed)+ B
Less retention (e.g. 10%)− (A + B) × 10%
Less previously certified− C
Less advance recoupment− D
Amount due this application= net

Assessing percent complete

Tracking to completion

Balance to complete = Contract sum − Total earned to date (+ approved variations)

A live progress-billing tracker shows earned value, the S-curve versus plan, and the remaining balance per line โ€” the basis for forecasting the final account.

๐Ÿ“‘ Using EngEst Pro

EngEst Pro’s Progress Billing tracker builds the schedule of values from your BOQ, records % complete per item per period, and computes earned amounts, retention, total to date, and balance remaining with a live progress bar.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.