Foundations are a stack of quantities per footing. Build a spreadsheet row per footing mark and the totals fall out.

Per-footing quantities

ItemComputation
Excavation(L + working space) × (W + working space) × depth; add side slope if unshored
Lean concrete(L + 100 mm) × (W + 100 mm) × 50โ€“75 mm
Structural concreteL × W × thickness + pedestal (h × a × b)
Bottom rebar matbars each way × (footing dim − 2 cover + hooks) × unit weight
Dowelscolumn bar count × (development into footing + projection + lap) × unit weight
Backfillexcavation − concrete below grade, × compaction factor
Advertisement

Combined and strip footings

Combined footings (two or more columns on one pad) and strip footings under walls use the same line items โ€” just longer plan dimensions and often a top mat as well as a bottom mat because the bending reverses between columns.

Waterproofing and protection

Where the water table is high, add a bituminous coating or membrane to buried faces, a protection board, and possibly a permanent dewatering allowance during construction.

Consolidate

Sum by footing mark → total excavation (m³), lean concrete (m³), structural concrete (m³ → cement/sand/gravel), rebar (kg by diameter), and backfill (m³ compacted). Spoil to remove = excavation − backfill, as loose volume.

๐Ÿ—๏ธ Using EngEst Pro

EngEst Pro’s Structural and Civil calculators work together on foundations โ€” enter footing dimensions and the platform returns excavation, lean and structural concrete, two-way rebar, dowels, and backfill as one consolidated BOM.

Put this on autopilot with EngEst Pro

Create a free EngEst Pro account โ€” 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.

Create Free Account โ†’ Run your first estimate in under 10 minutes.