Estimating an Electrical Bill of Materials from a Circuit Schedule
The circuit schedule tells you what protects each load. The BOM tells you what to buy. Bridging the two is disciplined quantity takeoff.
Conductor lengths
For each circuit: measure the homerun from the panel to the first outlet along the likely routing (not straight-line), add the run between outlets, and add vertical drops.
- Ceiling-height drop to a switch: ~1.2 m each.
- Drop to a convenience outlet: ~0.3 m each.
- Add 10–15% wastage for terminations, offcuts, and pulling slack.
Conduit
Conduit length roughly equals the single-run wire route (not multiplied by conductor count). Add couplings at one per 3 m of EMT, connectors at two per box, and one bushing per connector into a box.
Boxes, fittings, and supports
| Item | Rule of thumb |
|---|---|
| Junction boxes | 1 per lighting outlet + 1 per pull point |
| Device boxes | 1 per switch/outlet location |
| Conduit straps / hangers | 1 per 1.0–1.5 m run |
| Wire nuts / connectors | 3 per outlet box average |
Devices and equipment
Count directly from the plans: switches, receptacles, cover plates, luminaires, panelboards, breakers (by rating from the schedule), disconnects, and the service equipment. These are usually the largest cost lines.
Assemble and price
Group by category (conductors, raceway, boxes/fittings, wiring devices, luminaires, distribution equipment), apply current unit prices, add labour as a percentage or from a labour-hour table, and total.
EngEst Pro builds this BOM for you — every circuit you enter contributes conductor length (with drops and wastage), conduit, fittings, and device counts, and the platform outputs a categorised, priced electrical BOQ in your local currency.
Put this on autopilot with EngEst Pro
Create a free EngEst Pro account — 5 projects a month, all 8 calculators, PDF BOQ export. No credit card required.
Create Free Account → Run your first estimate in under 10 minutes.